The tender concerns the construction of a 110/20 kV transformer substation, the conversion of the 20 kV distribution network, installation of 54.6 km of medium-voltage cable lines, modernisation of 36 transformer stations and construction of 5 new transformer stations. The works last 30 months: 6 months for design and 24 months for construction and as-built documentation, with completion no later than 30 September 2029. The start of the contract depends on the signing of the financing agreement. The bidder must also take into account the performance guarantee, which must be provided within 5 working days after confirmation of financing.