Compliance requirements
The bidder must confirm the mandatory exclusion grounds in the ESPD, including participation in a criminal organisation and corruption. If an exclusion ground applies, the bidder may provide evidence of self-cleaning measures. The machine-readable notice did not include any more detailed exclusion grounds, so the official tender documents must be checked.
Qualification criteria and exclusion grounds
The bidder’s total net turnover for the last three financial years completed by the start date of the procurement must be at least EUR 30,000. The bidder must provide this information in the ESPD.
For managing the construction works, the bidder must have a site manager with at least Construction Engineer level 6, specialization in building construction, and competence in managing construction activities, or an equivalent qualification. Information about this person must be provided in the ESPD, and a copy of the diploma or professional certificate must be attached.
For all special parts of the works, the bidder must have competent specialists in the relevant fields, who will also be used in contract performance. The responsible electrical specialist must be either an electrical engineer level 6 or a specialist holding an B-competence certificate. Information about these persons must be provided in the ESPD, and copies of their diplomas or professional certificates must be attached.
The bid must be submitted in the required composition and include all documents and forms required by the tender documents. The bid price must be given in euros both excluding and including VAT, with two decimal places, and must follow the prescribed pricing table structure. If the bid is submitted by a person whose right of representation does not arise from law, a proper power of attorney must be attached. In the case of a joint bid, a power of attorney for the joint bidders must be attached. Where equivalence is used, it must be explained and evidence of equivalence must be included in the bid documents. The machine-readable notice did not include any more detailed requirements, so the official tender documents must be checked for any additional conditions or proofs required by the contracting authority. The machine-readable notice did not include any more detailed requirements, so the official tender documents must be checked for any additional conditions or proofs required by the contracting authority.